Dear Friend's

How i can maintain WBS Element variences in SAP ( Example: if their is 10 activities in wbs element which is to be completed within a Six Month duration, but only 5 activities are completed in Six Month & remaining are pending which may carry for next Three Months.So i want to maintain this plan vs actual variance with reason's )

How i can do in sap.

WBS Element - Plan - Actual - Variance - Reason

Civil Work - 10 activities - 5 activities - 5 activities - matrl shortages & insufficient fund

Regard's

Sandeep

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Use Statistical Key Figures for this:

KK01 - Create SKF's (activities like Nos. of Drawings etc.,)

CJS2 - Change (WBS Element) *Plan SKF's against the WBS

KB31N - Enter *Post the SKF's

S_ALR_87013548 - Statistical Key Figures/Periods * View Plan/Actual/Variance of SKF

You can enter Text's while posting the SKF's in transaction KB31N but I'm not sure about how this can be pulled into the report.

Regards

Sreenivas

stheurkar
Active Contributor
0 Kudos

Dear Shrinivas,

Thanks for replying.

I have followed steps given by you.But when i go for running the Tcode S_ALR_87013548 system is showing green error with message " Program 6PP7 does not exist"

So i am not able to see S_ALR_87013548 - Statistical Key Figures/Periods

Now what needs to be done. pls guide.

Thanks & Regards,

Sandeep

Former Member
0 Kudos

Seems we have some technical issue here. Take the help of Abaper or Basis to help you out.

Just see whether 336929 note are applicable to you, if yes apply it.

Regards

Sreenivas

Former Member
0 Kudos

Try below transaction:

GR5G - Generate

Generate the report group 6PP7 and check if report was successfully generated.