We are upgrading our system from 4.6 to ecc 6.0. We are currently doing SPAU activities in the ec system.

Along with many others, there are two nodes in the SPAU :

Maintenance and Transport Objects

Classes

Could any one can help me to know for which kind of objects these nodes are and how we need to deal with the objects under these nodes in SPAU?

Thanks for your help!

Points Assured to all helpful answers.

Regards,

Lalit Kabra

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos
Former Member
0 Kudos

Hi,

The adjustment of Repository objects is carried out with transaction SPAU. Only those objects that have been modified by you and are being redelivered by SAP in an upgrade are presented for adjustment.

Sap provides 14 days of time after upgrade to fix SPAU adjustments were as SPDD modifications needs to be adjusted during SAPUp phase and not after Prepare.

You can take the help of ABAP team to complete this adjustments.

In case you need any more assistance, then please get back.