on 01-16-2008 3:42 PM
Hi everyone,
I'm trying to find a MRP strategy for my FERTs and HALBs where my MPS (Ind req) is loaded at a PHANTOM HALB level creating dependend requirements on the Raw material ROH and the most important, the Sales Orders that are created on the FERT level must consume the Ind. req loaded on the HALB PHANTOM level.
Do you have some ideas on how to do this?
Thanks in advance,
Douglas
Hi,
How about:
1. MRP strategies: 40;
2. having an Order BOM with component of Phantom HALB.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.