Hi everyone,

I'm trying to find a MRP strategy for my FERTs and HALBs where my MPS (Ind req) is loaded at a PHANTOM HALB level creating dependend requirements on the Raw material ROH and the most important, the Sales Orders that are created on the FERT level must consume the Ind. req loaded on the HALB PHANTOM level.

Do you have some ideas on how to do this?

Thanks in advance,

Douglas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

How about:

1. MRP strategies: 40;

2. having an Order BOM with component of Phantom HALB.