hi

i have entered the date in ck11n as from 15.1.2008 and to date also 15.1.2008.

today if i try to confirm the order in mfbf the sysytem says that there is no std cost etimate.

if i try to run the ck11n today the system says that the price is updated in the material master.

i had run the cost estimate yesterday and also released.