We are capturing planned costs of service activity in our project.The issue we are facing is that all of the planned cost gets accumulated at the Latest Finish Date of the service activity.Our requirement is to capture planned cost uniformly or at least at the earliest finish date.
Is there any way by which we can achieve the above requirement?