Hello all,

We work with LPA scheduling aggreements and define one per year. So validity dates are as follow

validity start 01.01.2008

validity end date 31.12.2008

Unfortunetly, ME84 selects all LPA SA , even those that have their valididity date in the past : for example , it tried to create release on SA valide in year 2007. Consequence : many errors are generated and disturb the MRP controller.

Who has the solution ?