CM25 Dispatching Planned Orders with operations at differrent dates

364 Views

Hi,

We are using CM25 to manually dispatch planned orders.

For few materials, when we dispatch, the operation dates and times are not in sync with basic/production dates.

Even though planned order header dates(both basic and production) are starting and ending on same day, There are some operations whose start and end dates are one day ahead. And the worst part, the end time is more than what WorkCenter End time.

This is happening for few materials only.

Can you please suggest how can we stop dispatching the operations at different dates for all materials.

By the way, this difference is occurring after we save the dispatches too. we have unlimited capacity in the workcenters than the demand.

Appreciate your help.

Thanks,

Satya.