Skip to Content
0
Former Member
Jan 15, 2008 at 11:40 AM

Incorrect Result of Material Availability in production order

106 Views

Hi gurus,

we have a problem with material availability in production order CO01. When my list of materials is checked OK with option availability material and I modify the quantity of some material. With this modification, e.g. quantity 99.999, the logical result of my material availability would be NO OK, but the system answers is OK. I think he material availability doesn't recalculate the availability.

I will reward with a lot of points!!!

Thank you

Dan