Hi, Friends
I have come accross one issue where I found POC =120%. (By Cost proportionality) for one particular WBS element in project. Naturally when RA is perfomed, system is continuously giving Reserves for unrealised cost.Can actual POC be more than 100%.? If not what are the configurational measures one should take to avoid such scenario?
Adwait