SAP BPC 10.1 NW Standard ( Schedule Package Run )

I am triying to schedule a Daily package Run that will kick off every 30 min. The package is running only 1 time and it stop evethough I selected Every 30 min. I wonder if anyone out there encounter the same issue.

Thanks!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 03, 2017 at 06:57 PM

    When running package select Schedule (not Run and Schedule)

    Schedule task: Daily

    Every: 0 Day(s)

    Zero days!

    You can check schedule in SM37 - user: BPC_SERVICE

    Status: Finished - already done

    Status: Released - next run

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 03, 2017 at 05:42 PM

    Please find screen shot below: The Scenario is that I want the package to run every 30 MIN for a period of one week starting today at 2: 00 pm .