Creating Planned Orders with reference to Batch Characteristics

Hello Consultants,

I am running a scenario where for every material there are certain Batch characteristics maintained. Now, Planning for these materials has to be done by considering batch characteristics.

For example, if Material MAT1 is having a batch characteristic(say) BATCH_CHAR having values as CHAR1 and CHAR2 , then planned orders are needed to be created for combination of MAT1, CHAR1 for (say) 75 quantity and MAT1, CHAR2 for 25 quantity.

In MRP Screen or MD61 Screen, I didn't see anything like batch.

Pl guide.

Thanks,

Dheeraj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Oct 20, 2016 at 02:33 PM

    Hello

    MRP dos not run in a batch level and it does not consider batch characteristics at all.

    You can use variant configuration, as already mentioned, but then you will consider the sales order characteristics or the PIR characteristics, not the batch.


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 18, 2016 at 10:44 AM

    Hello Deeraj,

    I am not much clear about your requirement

    Please refer below document for your reference.

    http://help.sap.com/saphelp_46c/helpdata/en/94/79fb79c55511d1b5520000e82de178/content.htm?frameset=/en/94/79fb79c55511d1b5520000e82de178/frameset.htm¤t_toc=/en/cb/7f9b7043b711d189410000e829fbbd/plain.htm&node_id=44&show_children=false

    Please let us know if you want to more information.

    Regards
    Umesh Mali

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 20, 2016 at 10:42 AM

    Hi Dheeraj,

    You can achieve this by variant configuration.

    you need to create one characteristic as bom_qty. and in additional data maintain table - STPO - MENGE

    Assign dependency as $self.bom_qty = "75", if char 1

    and $self.bom_qty = "25", if char 2

    write if you need any more clarification.

    regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 21, 2016 at 07:22 AM

    Hello Dheeraj,

    As per my understanding MRP will not consider the batch characteristics for planning..

    i.e. System will generate the planned orders..

    during conversion from planned order to production order you have to select the batch characteristics

    Regards,

    Venkatesh..