In SOP i want SOP planning table to consider routing rather than considering Rough cut profile. Please tell me how to do

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Not possible...that is why it is caled as Roughcut.

But you can use the same workcemter for SOP and Routing(actual planning).

That should be okay with your requirement.

Answers (3)

Answers (3)

Former Member
0 Kudos

"SOP reqts i want system to consider all existing capacity reqt for existing Production orders taking place live in shop floor"

CAN THIS BE DONE ????#

I do not think so ?

Former Member
0 Kudos

Hi,

Its Possible. Got to transaction OPU4,in Rough Cut Scheduling put selection Id.(01) and select check box, scheduling & generate capacity requirements.

Former Member
0 Kudos

Dear Stuti Bagchi

But system will take the existing load and will show capacity is not avaioable...

Former Member
0 Kudos

Hi Rajesh,

I also thought that.But,strange thing I noticed that it does not consider the current load.It works on infinite capacity though the capacities of work centers were relevant for finite schd.

My reqmt. was such that,system should do SOP considering existing load also.

Kindly give your inputs for the same.

Former Member
0 Kudos

in my case it is considering

RCP is mainly for the future requirement where we dont have a routing...roughly we know the capacity and hr per To data.

If evener thing is known then why to use RCP...we can use difrectly capacity planning-detailed planning,...that was my point.

Former Member
0 Kudos

I like to convey it properly, My requirements are as below,

1. In SOP i know how to use RCP but i dont know how we can set to use existing routing for calculating availbale capacity. I have maintained routing, and when i try View-capacity situation-RCP-Show. it gives message no RCP exist. Is there anything we have to do in OPU4?. I want system to consider routing.

2. I have created Rough cut plan for two products P-100 & P-101 in Active version which uses same workcentre WC1. I will first post requirements for P-100 and in this case Avalable capacity was 100hrs out of which i used 70 hrs. remaining is 30hrs. Now i post reqt for P-101 and capacity reqt is 50 Hrs. In this case system should consider there is reqt for 70 hrs for P-100 and hence system should say WC1 has only 30hrs remaining. But here also system says there is 100 hrs available capacity. I want system to consider all capacity consumed by different A00 versions for diffeent material/PG

3. When i post SOP reqts i want system to consider all existing capacity reqt for existing Production orders taking place live in shop floor.

Thanks in avance.

Shrish

Former Member
0 Kudos

1. In SOP i know how to use RCP but i dont know how we can set to use existing routing for calculating availbale capacity. I have maintained routing, and when i try View-capacity situation-RCP-Show. it gives message no RCP exist. Is there anything we have to do in OPU4?. I want system to consider routing.

Yes, if you want to consider the routing prepared by you for RCP then OPU4 make the selection ID for routing in RCP = 01.

Make suer that the WC you are using in routing is having the usage = 009(all task list)

2. I have created Rough cut plan for two products P-100 & P-101 in Active version which uses same workcentre WC1. I will first post requirements for P-100 and in this case Avalable capacity was 100hrs out of which i used 70 hrs. remaining is 30hrs. Now i post reqt for P-101 and capacity reqt is 50 Hrs. In this case system should consider there is reqt for 70 hrs for P-100 and hence system should say WC1 has only 30hrs remaining. But here also system says there is 100 hrs available capacity. I want system to consider all capacity consumed by different A00 versions for diffeent material/PG

*Just try this oprion, As I know you need to create a product group involving all the products to be considered in that plant, aggregate that product group then conduct RCP with your routing as option 1, so that system will show the capacity requirement as a whole for the product group.*

3. When i post SOP reqts i want system to consider all existing capacity reqt for existing Production orders taking place live in shop floor.

It is possible, then you need to change the capacity planning settings in IMG for RCP to consider the production order and plan orders, as of now it is considering SOP orders only. I need some time as i did in long time back in 4.0B, I will check and come back if you findout please let me know, I have given you the idea just make a try.

Former Member
0 Kudos

In OPU4 i tried to change selection ID for RCP to 01. It saves. But if i reopen it is still 03. Am i doing anything wrong. I request for help

Shrish

Former Member
0 Kudos

nothing wrong..it should accept the value...just check in F4,,,is 01 value is avaialble?

Former Member
0 Kudos

Hi

I do not think it is possible & it is not the practice.

At SOP, you are supposed to chk capacity chk at very high level..

Regards

YMREDDY