Skip to Content
0
Former Member
Jan 12, 2008 at 07:54 PM

result of "indirect activity allocation"

69 Views

To my understanding "indirect activity allocation" can be used to auto plan receiver cost center / activity quantity by allocating planned quantity of sender cost center / activity type with "indirect activity allocation" cycles.

While after define the cycle (KSCB) and planned the sender cost center / activity type and receiver cost center / activity type (this is necessary for cycle to be correctly created and executed (KP26), cycle running is successfully.

The indirect activity allocation result can be seen in KSEP and KABP as well as KSCB.

The question and problem is the activity quantity allocated to receiver cost center / activity types CAN'T be seen in KP26, neither the activity quantity can be recoganized in price calculation for the receiver cost center / activity type.

Sincerely looking forward to any clue about:

1. if my understanding of receiver cost center / activity type should get the allocated quantity in "plan activity" field in KP26 (with standard layout 1-201) is correct or not?

2. if my understanding of question 1 is correct, then what's the possible problem cause the planned quantity is not allocated as expected?

3. if my understanding of question 1 is not correct, the what should be done to set plan quantity of receiver cost center / activity type AFTER "indirect activity allocation"?

Thanks a lot in advance !