Former Member
Jan 11, 2008 at 11:47 AM

Wrong BOM explosion in MFBF

66 Views

Hi

During MFBF bom is not exploding correctly for following structure which has a group bom. where as in cs12 or production order its exploding properly.

Total withdrawla qty should be

R1->2, R1->1, R2->1, R3->1 as per cs12

but, in mfbf its comming as

R1->1,R1->1, R2->1, R3->1

Am doing backflush (MFBF) for FER1 qty 1 without planned order. These is no phantom off indicator in BOM at any level.

Please help...

level, material, procurement type, quantity

1 FER1 E 1

2 SM1 E50 1

1 SM1 E50 1

2 SM2 E50 4

2 GRP1 E50 1

1 SM2 E50 1

2 GRP1 E50 1

1 GRP1 E50 1

2 A1 E50 1 usage pro 50%

2 A2 E50 1 usage pro 25%

2 A3 E50 1 usage pro 25%

1 A1 E50 1

2 R1 F 1

1 A2 E50 1

2 R2 F 1

1 A3 E50 1

2 R3 F 1

Regards,

Abhishek