Rework for Finished product

87 Views

Hi all,

I have a scenerio where finished product is send for rework.

I followed the following procedure for rework.

1. Create a production order without material in co07.

2. In the Settlement rule i assigned the corresponding cost center.

3. In the component overview, i added the finished product.

4. Using co27(Picklist) i issued the finished product for rework. The stock is reduced from the stores side.

5. We skip co11n.

I face problem when i do the the goods receipt in MB31 with reference to the production. The system throws error message that " No Valid order items exist for order XXXXXXX "

How to do the GR for the reworked completed finished component.

With regards,

Afzal