36 Views

Dear all,

If the system should do the capacity availability check what are the settings required.I have done the following settings. But still its not working perfectly.

1.In OIOI, I deselect the Check box "No check" and select the collective version as "3"(No creation of order if there is insufficient capacity")

2.I selected the suitable profile SAPPM_013.

3.In the workcenter capacity tab, in the planning details, i marked "Relevant to finite sheduling", "can be used by other opearations and "long-term planning".In the available capacity sub tab, i select the active version as "1" (Available normal capacity)

If i am trying to save the order after creation, it is getting created.Only it is showing the capacity overload, when we do the check manually by the main menu-Order -functions.

Plz guide me for the missed settings