Hello,
I have a simple project with one phase and one task inside there. I put the the planned date for the project, so the task dates inherit them, as expected.
The problem happens when in Aditional Data (for the task) I put the actual start and finish dates. When I do this, the planned dates are overwritten with the actual dates! So I'm not able to compare the planned dates vs. actual dates for the task....
Do you have any suggestions please?
Best regards, Gustavo