on 10-17-2016 6:42 PM
Hi,
I created a new Material Status (OMS4) and when I run CK11N for material with this status, I would like that system showing a warning message at the moment the costing run start.
I tried change the Mat. Cost Estimate Procedure on OMS4 using one of the 3 first options below, but I didn’t understand the diference among.
When I selected the options C and D, CK11N shows the message “Costing is not allowed for material/PPS status”.
I hopped that selecting the option A, the system showing a warning message at the same time the options C and D however costing, but it didn’t show anything.
Questions:
What’s the diference among optinos “ “, “A” and “B”?
Is it possible the system show the warning message “A” at the start of costing (as below)?
Thanks in advance.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.