Skip to Content
author's profile photo Former Member
Former Member

not able to change PIR of type VSEV

I am not able to change a PIR of type VSEV,through MD04.

A planned order also exists for this PIR.

When I go to MD62, I am not able to see this PIR.

Is it possible to change this PIR? If so how?

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 08:20 AM

    which stg grouop you are using?

    There can be a change that PIR is completely consumed by planned order or PR...just check and come back with stg group

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 08:22 AM

    System propse Req Type(VSEV) as per the Planning Strategy maintained in the Material master.

    To change the VSEV you have also to change the Planning Strategy type in mat master.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 08:30 AM

    the planning strategy is Z7 which is similar to strategy 60.

    The difference is,Reqmt type of customer reqmt is ZSVV,with the requirement class as Wrhse cons.plng mat.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.