Hai friends,
am a BW consultant. I have to work on PP module to extract datasources into BW side. I dont know anything about PP module.
Can anyone tell me,
what is the meaning of all these,
Planned Order
Production Order
Production Order Released
Forecast
Pegged Requirement
Status
Earliest Start
At Operation
Operation
Operation Short Text
Material
Material Description
Quantity
Rem Hours
SetupTime
MRP Controller
Production Schedular
Planned Released date
Actual Release Date
Difference
Planned Finish Date
Actual Release Date
Float Before Production
Project Definition
WBS Element
Line Item or Network.
And also please send me the documents related to PP, tables, datasources, data flow in PP.
Guaranteed points will be given.
thanks in advance
with regards,
siddharth
Hi,
Planned Order A request created in the planning run for a plant to trigger the procurement of a plant material for a certain quantity for a specific date
Production OrderProduction orders can only be processed and backflushed in the R/3 system. Planned orders that were created in APO are converted to production orders in the R/3 system. The current production order data relevant for planning is transfered from the R/3 system to APO.
Production Order Released this is manual or auto release once you release then status gets changed auto.
Forecast - for this you have to maintain forcast based parameters in mmr.
Pegged Requirement- this is component requirement after mrp run.
Status-it a system status field when ever any action gets executed it will get changed
Earliest Start- it a schedule start date in order
At Operation - at operation level
Operation - what you included in routing
Operation Short Text- detail info. about operation
Material - this is the main ingredient in mrp and overall business
Material Description- detail info. regarding the material
Quantity - this is the field in order and bom itself.
Rem Hours-its a repetitive manufacturing profile in that rem hours are there that you have to maintain
SetupTime- this is regarding the work center and its capacity related term
MRP Controller- its a key person when mrp run is to take place normally he is responsible - In mps manufacturing his role is vital
Production Schedular - its a related to order scheduling where it is assigned to production /process order
Planned Released date- whenever planned order
Actual Release Date - this is actual date of order
Difference it is vaience amt.of order
Planned Finish Date - its related to order date
Actual Release Date- its related to order date
Float Before Production- its related to schedule margin key and you have to define it in mmr
Project Definition - its related to ps module there you have to define your prooject
WBS Element - its a wbs element in ps module and when engineer to order scenario is there ther you have to define a wbs element - tcode- CJ91/92/93
Line Item or Network.- it is also related to ps module and that also you have to define by t code - CN01/02/03
reward points if useful to you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi siddharth,
*For PP Flow* Gothrough below link
https://www.sdn.sap.com/irj/sdn/wiki?path=/display/erplo/erp+pp&;
*For PP Table*
http://www.sap-img.com/pp009.htm
http://www.sap-img.com/production/sap-production-planning-table.htm
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I feel you better goto help.sap.com and search for each word you will ghet very good information of all these words..I can give you definition of all, but i feel the first option is better as SAP help is very good for this.
About data sources and other BW data just the following link
http://help.sap.com/saphelp_nw70/helpdata/en/29/79eb3cad744026e10000000a11405a/frameset.htm
see in supply chain folder...you will get all required
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.