We have set a release stratergy for PR were in after release of PR(changebility factor set as 1 in release indicator), it cannot be further changed. But the problem we are facing is in case if we want to short close the PR after the release, system is not allowing to set the completion indicator(it is not going to change mode).

We have already tried MASS MAINTAINACE OF PR to short close, but we don't have option to set the completion indicator.

Please advice how to short close a PR in the above mentioned scenerio.

Best Regards

Arihanth

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 08:27 AM

    Hello Arahanth

    Please see whether the following works

    Goto Tcode MASS, Input Object type = BUS2105 and then execute.

    In the subsequent screen select row Purchase requsition table name EBAN and click on execute button

    Next screen click on choose selection feilds button which is 4th buttom from left a pop up window will appear here on the right grid serach for closed select that row and click on left arrow button and save entires as a variaint with your own name.

    This should work

    Regards

    SE

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 06:35 AM

    Hi,

    Go to OMF2 -> SELECT NBB -> Select deadline monitoring and check the status of field Indicator : requisition closed.

    Reward if helpful.

    Regards,

    Chetan.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2008 at 06:40 AM

    HI,

    there is no standard option to short close the PR by MASS.

    u have to short close PR manually.

    short closing the PR manually for the release PR, change the indicator in the release strtagey of PR

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.