on 01-10-2008 5:07 AM
Dear All
I have created production order against one specific BOm
Then i changed the BOM line items & again i have created one more production order but new BOm items are not updaetd in the new production order
pl help
regards
Kiran
Hi Kiran,
You have changed the BOM components in the old Production Order which will be valid only for that Order, To make it effective for all the new Production Orders to be made, You have to make the changes in the Master Data ie BOM ( TC CS02) .
Regards
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You might not have deleted the old line item, instead erased it and typed the new line item in the same place itself..
you have to delete the old line item , save the BOM and then you need to add new line item.
That is why the problem exists.
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can you tell me what you have changed in BOM? have you used change number?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran,
Please let us confirm onething, after cretaing production order where u have u changed BOM Component ie in CS02 or in C002.
If u have changed at Production order same will not be upadted at BOM master. That`z why ur getting old component for New order.
u have to change at Cs02
if not plZ Explain.
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, kiran
Whatever Krishna is saying is perfect. u have to go in t code cs02 & make changes over there , so that it will be effective.
And suppose aftre creating production order u wana change it then also u prefer tcode cs02 make changes & in co02 read pp master data so that it will give u the necessary result.
It will definetly work. Try this . PLz reward if found helpful.
Regards ,
sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have a look at your prodcution order Header details master data.
which BOM and which alternative has been selcted?? from there you can easily get your error.
Have a look at Valid from date and Explosion date?
comapre your both the orders.
you will get your error.
Regards,
Pravin Mukkawar
TCS gandhiangar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kiran,
I would suggest you to check the Valid from Date of specific component you are taking about, probably you would have added with effectivity date 10.01.2008. Now when order is exploded it is looking for valid components as on 03.01.2008, this may be the problem.
A simple suggestion here is that you execute Read PP Master data for this order in the change mode(CO02), from the menu bar Functions--->Read PP Master Data. You would get a Pop-up screen Read PP Master data.. here in the screen "Cont." button. One more screen pops up, here in the BOM explosion date you give it as 10.01.2008. Hope you will get the new component also in your production order now.
Regards,
Prasobh
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.