In production order the cost of the production order planned and actual are seen in one report cost trend in production order.

In this the goods issue rows shows there with respect to the BOM COMPONENTS . But in my case the planned cost for each component item is showing in diffent row and actual cost of each componet item is shown in diffent row. though it is the same componet it is showing in different row.

how to control it in the layout or any other way to control it. because i want to see the variance of the material with respect to planned and actual.

please suggest