Hi
I have an issue for purchase order. We are procurring some material for a project. The account assignment category used is Projects 'P". In account assignment we are entering the WBS Element. However, the cost for the same does not flow into the cost center for consumption account. We have 1:n relation between profit center and cost center.
How can we capture the cost in cost center for consumption account at the PO level using account assignment category P.
Regards
Sanil Bhandari