We user t-code C011N to do order confirmation.
For example:
CO01 create a production order: 1000440. Material: 8006086519
This production order's routing have 3 operation.
0010 0020 0030
When user use C011N to do order confirmation 0010 in 2008/01/01, We will use the enhancement CONFPP05 to create customize batch into table ztppm001.The batch is refer to the first confirmation date.
Like follow: Talbe: ZGPPM001
Production order Material batch
100400 8006086519 20080101
In 2008/01/10, when user use CO11N to do order confirmation 0030.The operation will do the GR for material 8006086519.
We want the GR batch is 20080101.
I cann?t find any enhancement to realize the function.
Could anyone give me some idea?
You can download the question.There are screen description in the document.
[url]Http://www.seejob.net/CO11N Issue.doc
Cheers! Thanks in advance.
Regards,
Eric .