Hi friends,

I have doubt on calculating product cost in BPS or CO-PC.

My customer wants me to extract all routings and bill of material data to BW then they would like to run BPS functions for calculating product costs and finally calculating COGS. But I prefered to calculated plan unit costs in CO-PC. I have sales plan quantities in BW. I retract them to R3 MRP. I took MRP production hours to CCA. I retract production costs to CCA. I calculated unit prices.Finally I executed costing variant and save the costing result, extract them to BW.