on 01-08-2008 4:52 PM
Can I calculate cycle time from generating a need to P req and P req to creating PO and from PO to material receiving ?
Hi
the Cycle time depend upon the circumstances
like when you want the material, what is the lead time etc............
if u want you can calculate
total time to get the material into your stock =10
u can divided this time into no of segment
PR Processing time=2days
PR to PO time =3 days
PO to GR time=5 days
the total lead time is 10 days
these time depend upon the vendor as well upon buyer
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no such funcitonality to calculate this kind of time and what is the need for it.
PR,PO etc are transaction document so it's depend on the user when and how they are creating.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.