Can I calculate cycle time from generating a need to P req and P req to creating PO and from PO to material receiving ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

the Cycle time depend upon the circumstances

like when you want the material, what is the lead time etc............

if u want you can calculate

total time to get the material into your stock =10

u can divided this time into no of segment

PR Processing time=2days

PR to PO time =3 days

PO to GR time=5 days

the total lead time is 10 days

these time depend upon the vendor as well upon buyer

Thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

There is no such funcitonality to calculate this kind of time and what is the need for it.

PR,PO etc are transaction document so it's depend on the user when and how they are creating.

Former Member
0 Kudos

Hi,

Management wants to know the cycle time from the past data.

Former Member
0 Kudos

Then activate the vendor evaluation functionlity in the purchasing which can give the cleare idea if vendor performance.

Former Member
0 Kudos

Hi,

To know the cyccle time from past data you create Z prog

For PR table EBAN

For PO EKPO

for GR MSEG

for IR BKPF is header table

from there you can compare posting dates ( Pr creation date and GR posting date) and can able to calculate cycle time for past transactions .

Regards