Hi vishu,
check the over load for work center at CM01, here u can decide which prod order should be despatched or rescheduled.
then goto cm21, system will list out the all teh opeartion realted to production order number in teh order spool table(Bottom). select the operation and use "despatch" option or manually u can "trag" the operation to workcenter table (top), now opreation will be despatched to workcenter on a particular date, now system reschdule opeartion and set opeartion status as despatched (DSPT) & save.
if u want to finite scheduling select "strategy profie" relevant for Finite scheduling at cm21 and actiavte "releveant for finite scheduling" at workcenter before leveling.
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can select the order and press F5 key or simply click on dispatch button given .
reward if useful to you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.