Hi BW Gurus,
Currently am working on implementing the Purchasing componant of Logistics aplications.
I have gone through some informative documents posted on this forum regarding Lo-Cockpit, setup and the steps involved.
I want to hear from those who have implemented Purchasing componant in there past expereince regarding few issues:-
ECC6,BI-7...GO-Live
1) After filling the setup-tables(Full), how to split the Delta-Inits from BW side, for example based on PO ranges or have one big init request??
2) if you can suggest any real-time issues that might occur during the go-live phase. that will be a big help!
answers will be rewarded.
thanks
Kind Regards
Rao
Hi Rao,
I can suggest you to take a look at the business content delivered from SAP for procurement.
http://help.sap.com/saphelp_nw70/helpdata/en/ed/62073c44564d59e10000000a114084/frameset.htm
I suggest you to use 0PUR_C01,0PUR_O01,0PUR_C09 cube and ODS.Just give a close look the object above.
For any questions let us know.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We used the following steps, loading to ODS with key figures set to overwrite -
1 - initialized delta without data transfer
2 - built set-up tables (OLI3BW) for all history
3 - did full loads (with repair status) to ODS, 2 years per load due to data volume.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
10 | |
10 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.