Hi Gurus,

Can we post an SKF with the values planned for a cost center?

The process should result in posting an SKF document(KB31N) by picking the planned values for cost centers/groups.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Yes we can post the values if you mintain the Planned SKF with Cost centers in KP46 and in KB31N you enter the actuals against the planned values.

Regards

Balaji

Former Member
0 Kudos

Can the posting be done automatically is my question. With out me checking the planned vaules and posting them as actuals

Like...if I give the cost element/grp and cost center/group and execute the transaction...it should pick up the planned amounts in that cost element and cost center combination and post as skf in KB31N