Hi,
We have implemented SRM 4.0 (SP07) with extended classic scenario.
we created a PO through "Process Purchase order" & referred a line item to a contract (in the sense we are creating a call off) however when PO is ordered, system doesn't pick currency, Payment term & incoterm
maintained in contract header level into PO header but instead pick
that data from Vendor master in SRM (BBPMAININT).
Here is what we have maintained in Contract & Vendor master.
Contract No: 4800002324
Contract Currency: Euro
Payment Term: 60 days net
Inco term: CIF
Vendor master details
Vendor no: 106864
Currency: SEK
Payment term:030N
Inco term: DDP
If we perform similar test in R/3 then system behaves according to
standard.System copies currency, payment term & incoterm from contract header into PO header.
If this behaviour is possible in R/3 then why not in SRM ?
Has anybody witness simmilar problem in SRM so far..?
Any help will be awarded with full points..
BR
Bharat M