Hi all,
Why will a calculated std cost est not be equal to my standard price in my costing 2 view on the material master? For ex:
I calc a price for material 1 = R11.50
The price in the material master (MBEW-STPRS) is R10.80.
I can see that the difference is some activities for one of the operations in my production process, but it does not show on my material master.
Can anyone suggest a solution?
Thanks,
Hein