in balnket po we do not go for GR step and directly we r doing the invoice verification an we manually gets a confirmation from the cost center by asking a user

But

my question is how the system comes to know that we have recived the material i mean hwo we r going to map it into sap

Edited by: baxter jas on Jan 7, 2008 5:06 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Baxter,

Its difficult to know from the system since there is no GR.It can be confirmed only through user from the cost center during invoice verification.

Vivek Maitra

Former Member
0 Kudos

is it onlya way vivek to do for balanket po

Former Member
0 Kudos

Yes. A blanket PO is meant to be used this way only. So you will create blanket PO only for low value items - i.e. items where the cost of doing GR, GI, etc (and tracking) is more than the purchase cost.

If the item does not fall under this category, you should not use a blanket PO, but a normal PO or a contract.

Lakshman