how to transferiing asset plant to plant

Former Member
0 Kudos

We are transferring asset from one plant to another plant, how it is to be done in system with a STN print of the asset which we are transferring.

please help me

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

go as02

in <time-dependent> tab select further intervsls

slect add intraval, enter today date.. and you can change plant.

Regards

ss

Former Member
0 Kudos

In asset mangement there is no tranfer between plants. (only for company code's and BA)

In the tab (AS02) you can change the plant (cost center?) or create a new time interval.

Paul