Hi all,
We are trying to activate workflows for change documents in cProjects 4.0.
We have performed the following steps:
1. Activated the workflow ( WS 28700006 )in cProjects IMG.
2. In transaction SCDO
Enter DPR_PROJECT in the table.
3. In transaction SWED
Change document object DPR_PROJECT
Leading table in change document DPR_PROJECT
Change document key with structure DPR_PROJECT
Action: Change X
Structure DPR_TS_BUSINESS_OBJECT_KEY
Function module BAPI_BUS2175_OBJECT_KEY_SET
4. Change document DPR_PROJECT
Object category BOR object type
Business object type BUS2175
Event CHANGED
On change X
We have also maintained the field restrictions for DPR_PROJECT and DPR_TASK
However, we are still not able to find any entries in the table swwwihead, which indicates that the workflow has not been triggered.
Kindly suggest if we're missing anything.
Thanks,
Vivek Pandey