hi experts,

can anybody give me the procedure to apply delta's in BI 7.0

thanks & regards

venkat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

It is same as in BW 3.X.You need to make first initialization then you can get delta records.

Regards.

Answers (3)

Answers (3)

Former Member
0 Kudos

R/3 to PSA , INIT and DELTA infopackage

PSA to Datatargets, DELTA Dtp only

Hope it Helps

Chetan

@CP..

Former Member
0 Kudos

Hi everybody,

Pls explain me clearly, I am still not able to understand.

Till full load no need of creating the DTP?? Till full load we can make it Infopackage so the full load datas will be there in PSA.

After that creat the DTP and give delta or how it works pls explain me the delta works here.

Thanks

Sathiya

Former Member
0 Kudos

Run the Infopackage - say Init with data transfer - This will load Req 1 to PSA.

Run the Delta DTP - This will laod Req1 to Target - ODS, Cube....{ No Init is reqd for DTP's - First Time DTP is acting like Init with data transfer }

Tommorow, when you run the Infopackage with Delta as update type - Req 2 is loaded to PSA

Run the Delta DTP - This will only load Req2 to Target - ODS, Cube....

Or

Run the Infopackage - say Init with data transfer - This will load Req 1 to PSA.

Run the Full DTP - This will laod Req1 to Target - ODS, Cube....

Delete Req1 from PSA

Tommorow, when you run the Infopackage with Delta as update type - Req 2 is loaded to PSA

Run the Delta DTP - This will only only laod Req2 to Target - ODS, Cube....

{ First Time DTP acting like Init with data transfer }

Note : Delta DTP will only fetch unloaded requests in target from PSA.

Former Member
0 Kudos

Hi,

So only one DTP is sufficient to load the full and delta data right??

If we have not deleted the previous req in PSA and loading the present req to DTP will this not take the previous req from PSA right??

Deleting the prevoius req and loading the todays req this option is there in process chain is there any option without using the pc??

Pls let me know.

Thanks

Sathiya

Former Member
0 Kudos

hi ,

There is no difference between BI7.0 and BW

BW 3.5 using infopackage ur loading the data upto cube level ,

but In BI 7.0 using infopackage u can load the data upto PSA level, from there u can run the DTP,

u can follow the same data loading as BW 3.5 procedure like full, Init, Deltas, upto PSA level in BI ,after that ................ From PSA to Cube follow these

In BI 7.0 also if u want to run the full load u need to create *DTP for Full load* ,if u want to load delta loads u need to create DTP for delta,_

If u run the full load ,The DTP is fetching the whole PSA level data at time , even though PSA got delta also ,if u run Full load it combines all request in to single request and sending to Cube ,

in case if u runThe DTP for delta , it fetches the only Delta loads what PSA table got deltas

i think now u can understand the situation,

if ur not understand i can explain clearly

if it is useful assign points

Regards

prakash.v

Former Member
0 Kudos

The deltas in BI 7.0 are a bit different than in 3.X.

DTP calculates the delta from PSA based on request that has not been uploaded into the target.

Below are some scenarios & options to handle them:

Datasource - Delta

Info Pkg Mode - Init (1st time); Delta (repetitive)

DTP Mode - Delta

Datasource - Full

Info Pkg Mode - Full

DTP Mode - Delta (Have to delete previous request in Cube through Pr Chn)

DTP Mode - Full (Rarely used; If used then all previous requests have to be deletd from PSA & cube. Else data will double up).

Look into Features [http://help.sap.com/saphelp_nw70/helpdata/en/42/fa50e40f501a77e10000000a422035/frameset.htm]

Hope this helps,

Award points if it helps.

Thanks

Vishno.