CAN ANY BODY GUIDE ME, PLS GIVE ME THE CONFIGURATION STEPS FOR COSTCENTER PLANNING, HOW CAN WE MAINTAIN THE PLAN DATA FOR COSTCENTER.

REGARDS,

SWATHI

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member588240
Contributor
0 Kudos

The following are the configuration steps for Cost Center Planning. You have to configure the steps in SPRO.

1. Create Planning Layouts for Cost Element Planning/Activity type planning/Statistical key figure planning

2. Define User-Defined Planner Profile

3. Define Distribution

4. Create Assessment Cost Elements

5. Define Allocation Structures

6. Define Assessment

7. Define Activity Types for Indirect Activity Allocation

8. Define Indirect Activity Allocation

9. Define Splitting Structure