hi,
i have one problem. earlier in our project we were creating each material for each opeartions. for example if a Finish material is having 10 operations, then we were creating 10 semi finish materials and were giving processing cost for each operations/semi finish. but they said they don't need this type, bcoz they have to create production orders for each semi finish/operations. they want in simple way. actually the scenario is, they have 4 units and some time they go for sub contracting. if a Finish matrerial is having 10 operations and being done in different units, first 4 operations are done in first plant, 2 operations are done 2nd plant and 7 operation is a subcontract one and remaining operations are done in first plant, then we create 4 semi finish materials. in this way they want processing cost for each operations. please help me.