on 01-03-2008 8:09 AM
The problem I have is that after PO output there is a need to change the price of an itme in the PO and the release strategy has to be reset.
The message I receive when changing the price is, "Purchasing document already outputted (release will not be affected) Msg No. 06689" What I need is the opposite, To reset The release strategy.
Thanks,
Itzik Eshed
Make following change in customization of release strategy
Use for release indicator
6 - Changeable, new release in case of new strategy or value change/outputted
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
What is the Changeability of Purchasing Document During/After Release against the Release Indicator??
Regards,
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.