Capacity Planning - Please suggest

21 Views

Dear All Hi,

Scenario is as follows.

FG Requirement qty : 25 units

FG Requirement date : 15/01/2008

Capacity out put / day : 5 units

RM (one of RM) lead time : 4 days

Now,

Capacity is not available till 20/01/2008

In this case HOW can i make system to schedule my planned order on 21/01/2008 & similarly propose PR dates for RM's considering their lead times.

this something i have read about finite planning & finite scheduling, please help how to capture these settings in system.

Thanks in advance.