Dear SAP gurus,

I'm using MRP to generate PR. These PRs then are subject to release strategy. When the PR is still not released, i can change the quantity. However when the PR is already released, I cannot change the quantity (the quantity is . Note that I already put changeability for the relevant status to 4 and i put the tolerance to zero.

Do we need to maintan another configuration?

Please help.

John.

Accepted Solutions (0)

Answers (2)

Answers (2)

sap_2605
Active Participant
0 Kudos

I have checked the screen setting tied to released status. Apparently the screen setting for the quantity is not editable, I changed the screen setting thus solved this issue.

Former Member
0 Kudos

hi

First cancell release in ME54 and then try to change Qty.