Hello;

I want to know complete cycle for condition based maintenance (step by step); I have checked all the relevant threads for this, but could not get the complete solution.

What I understand is: (Pls. correct me where I am wrong)

1) I'll have to activate IMRC0001 exit first ( what is the difference between IMRC0001 & IMRC0003?)

2) Create a measuring point on technical object (This should NOT be marked as a counter as this is used to capture instantaneous values)

3) Set the target value, upper & lower limits for the measuring point.

4) After doing this, I think it is not required to create a maintenance plan, task list etc for the equipment

5) Now in the the include "ZXMRCU01" ABAPer needs to write a programme based on the client need (such as creation of notification , order or some event). In the same programme ABAPer needs to write a logic, if its an order then what should be the operations, material in the order.

( Hence NO maintenance plans & task lists can be used for condition based maintenance)

Then based on the reading fetched from SCADA, RFC or manual entry; the desired ouput can be achieved.

Your views on this pls.

Points assured.

Thanks & Regards

Hemant