planning horizon

21 Views

Hi Gurus,

i maintained ph 10 days at plant level, now i created a ind. req. of 100 cv for finished product on 01/12/07, i am running MRP today( 30/12/07) by using MD02, the system is generating planned order i set processing key NETPL, why system is renerating requirement.

Vikas