Hi all

We have 4 plants(P1,P2,P3 &P4) under one co code out of which 2 (P3 &P4)plants are newly created

In P1 and P2 already masterdata is there and all the transactions are working fine.

We have created a BOM1 in P3

BOM components are

Material M1 is Fert & M2 is FERT and is already existing in Plant 1 & 2

we have extended these material in plant 3

For plant 3 ,M1 is finished Product with material type FERT

It requires M2 as component in BOM, so here M2 should be a Raw material or semi finished material

Unfortunately we have extended the Material with same material type in Plant 3,

we have also created Plant 1 as vendor

Now while taking MRP it is considering 2 material from Plant 1,which is wrong

What can be the cause of this and what is the remedy??

Solution for this problem will be duly rewarded

Thankz in advance

shailesh