Hi,
In activity price calculation I execute in following sequence
1) KP26-Activity Planning
2) KP06-Cost element Planning
3) KSV3-Cycle for distribution
4) KSS4- Splitting
5) KSPI- Price calculation
Now what I want to ask is if I want to change the figures of Cost elements or Activities , can I do so although I have executed KSPI ? Can I get revised activity prices based on the changes I make in KP06 & KP26? Are the prices reposted in KSPI?
Please help me. Bit urgent.