Dear All
In my project , we r not using Notifications for Maintenance requests.
Directly a Maintenance Oreder will be Created , and the planner will approve it.
But , if the Created Order is not technically or Economically feasible, then planner will not approve it and he will change the User Status.
But the That Order is Still captured in IW38 transaction.
The planner doesn't want it to appear in IW38, as the Order is already rejected.
I have tried different Combinations ,like putting Deletion Flag,Locking,creating a new user status.
But the Order is always captured in IW38.
Is there any workaround possible in PM Module?
Regards
Manish Bansal