Schedule agreement MIGO

Hi All

I have created a schedule agreement with LP.

I have also created delivery schedule for this.

Now while trying to do MIGO against this schedule agreement number , it is giving error , no selectable items.

What can be the possible chances for this?

Kindly advise.

regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

7 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 08:29 AM

    Hi PVS,

    check the GR date,

    if it is prior to the schedule date it will give this error,

    check the SA is released or not,

    reward if useful

    lakshmi reddy

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 08:30 AM

    Hi,

    check whether vendor confirmation is reqd before migo and that u will do in VL31N.

    and start delivery date in del schedule.

    Thanks

    Suresh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 08:30 AM

    Dear all

    Kindly check in T.Code:-Me38,Schedule date mentioned should be past date of GRN date.

    Edited by: Chandra Mohan on Dec 28, 2007 9:52 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 09:11 AM

    if the MIGO date is earlier than the Schedule date, then it will show this error.

    put the schedule date same as MIGO date, it will accept.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 08:29 AM

    Hi,

    Maintain delivery schedule for today's date, then only you will be able to proceed the Goods Receipt.

    Regards,

    DilliB

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2007 at 09:06 AM

    Dear PVS,

    Please check whether deliver schedule lines are released.

    GR date is on or after schedule line date.

    System will not allow GR before schedule line date.

    Reward if useful,

    Vivek Maitra

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 28, 2007 at 09:39 AM

    Check whether 1) the Purchase order is released

    2) Already GRN might happen

    G.Ganesh Kumar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.