Dec 28, 2007 at 07:46 AM

order start date with respect to RM planned delivery date clarification

300 Views

Hi all,

Please give me the suggestion for the following scenario.

MRP processed date 28/12/2007

RM planned delivery is 6 days

PR ( planned & delivery) date is 03/01/2008.

Schdule FG Production order start date is 28/12/2007,

But the schedule order start date should be after the procurement of RM & in that case the schedule production start date should be on or after 03/01/2008.

Please suggest.

thanks in advance