Automatic confirmation and goods movement for production orders

former_member445197
Participant
0 Kudos

Hi All,

Please let me know if it is possible to implement the following 3 steps using standard SAP PP for a FERT with a BOM containing a HALB, which in turn has a BOM containing a ROH.

When FERT production order is confirmed by the user:

1. FERT goods receipt and HALB goods issue are automatically posted against FERT production order

2. HALB production order is automatically confirmed

3. HALB goods receipt and ROH goods issue are automatically posted against HALB production order

Accepted Solutions (0)

Answers (1)

Answers (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

Did you tried with the Collective Order functionality ?
For more info on Collective orders, search for the existing Blogs, you will get detailed info

Thanks & Regards : Raja Sekhara Reddy

former_member445197
Participant
0 Kudos

Thanks for the reply, I will check on this and provide an update.