Skip to Content
0

Automatic confirmation and goods movement for production orders

Oct 27, 2017 at 08:26 AM

88

avatar image

Hi All,

Please let me know if it is possible to implement the following 3 steps using standard SAP PP for a FERT with a BOM containing a HALB, which in turn has a BOM containing a ROH.

When FERT production order is confirmed by the user:

1. FERT goods receipt and HALB goods issue are automatically posted against FERT production order

2. HALB production order is automatically confirmed

3. HALB goods receipt and ROH goods issue are automatically posted against HALB production order

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

RAJA SEKHARA REDDY BANNURU Oct 28, 2017 at 06:15 AM
0

Hi

Did you tried with the Collective Order functionality ?
For more info on Collective orders, search for the existing Blogs, you will get detailed info

Thanks & Regards : Raja Sekhara Reddy

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks for the reply, I will check on this and provide an update.

0