I created a bill of material for pieces that we need to get painted y/o galvanize. I specify the various components that make up that product and the appropriate quantities of the components. The idea is the system generates a requisition just for the top number which one, once again has all the components on it. The problem I have is the system generated a requisition for each component like if I am going to get a service quote for all and I am not. We made here each component and we already have it when I need to get it painted or galvanize as a unit.

After I get these pieces painted or galvanized. These same pieces will be part of the final assembly of the product to be sold.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Marbelys,

In your case you have to take planning run with "Single Item planning".The planning run is therefore executed at single level i.e first level ie.Finished item.

To run single item planning choose logistic - MM - MRP - MRP - Planning- Single item single level.

Hope this will solve your problem.

Reward if useful,

Vivek Maitra

Former Member
0 Kudos

While you are creating running the BOM. Run with Multilevel BOM Exploding so that

all the componenets of the BOM will get exploded.